What I had at this point was a new concreted work area that abutted the existing concrete work areal. The old area is all clear span, thanks to the massive double 18 inch LVL beam that we installed and an even larger cable supported beam set up that was done some time before WWII (the big one, as Archie Bunker would say). The first pic below shows how they replaced two (2) support posts with the cable tie system. That would be interesting to watch.
To go clear span on the entire work area would have required new construction to the point of meeting all modern building codes. I don’t believe we even had a modern building code when this was built in 1919; and I sure wasn’t willing to try to bring this structure up to modern standards. May as well bull doze it and start over.
I posted the pic of the couble 18 inch LVLs a while back, but here is a reminder.